Downtown Gathering Space

Project Description: This project includes improvements to the downtown area behind Summit Coffee and The Pickled Peach.  The current phase under construction is the pergola.

Project Status: The pergola was redesigned to accommodate Duke Power underground structures in the area. The project has an expected completion date of May 25, 2023.

Page Updated: 03/21/23

  1. Project Info
  2. Timeline
  3. Documents
  4. Contact

Project Info

  • Project Name: Downtown Gathering Space
  • Cost $264,000
  • Funding Source: state funding, Capital Fund
  • Funding Status: Approved in the 2021 fiscal year budget