Project Description: Fisher Farm Park is currently served by portable toilets and a dedicated changing station for mountain bikers. The site has hosted large events in the past and will in the future. Water at the site is provided by a well, and sewage is processed by a septic field. Electric power is available on site. The town will be constructing a functional, low-maintenance restroom facility in keeping with the rural nature of the property. The town is also interested in a restroom facility that is resource efficient, featuring products with minimal negative impact on the environment.
Project Status: Design started
Page Updated: 01/27/2021
TASK | DURATION (DAYS) | COMPLETION DATE |
Proposals due | Friday, October 2, 2020 | |
Notification of award | 26 | Friday, October 28, 2020 |
Design commencement | 49 | Wednesday, December 16, 2020 |
Design Review Board review | 63 | Wednesday, February 17, 2021 |
Conceptual drawings complete | 9 | Friday, February 26, 2021 |
Permit drawings complete | 28 | Friday, March 26, 2021 |
Pre-bid meeting | 14 | Friday, April 9, 2021 |
Bids due | 14 | Friday, April 23, 2021 |
Contract signed | 21 | Friday, May 14, 2021 |
Notice to proceed | 7 | Friday, May 21, 2021 |
Permitting | 28 | Friday, June 18, 2021 |
Construction complete | 90 | Thursday, September 16, 2021 |
Town of Davidson
Doug Wright, Project Manager
Consultant
CDesign, Inc.