Project Description: This project includes a sidewalk along the east side of Grey Road, from Concord Road to Wolfe Street. The sidewalk will link Grey Road property owners and the St. Albans neighborhood to Concord Road, and then to downtown Davidson.
Project Status: We have re-designed the project to reduce the cost of the storm water portion. The new engineer’s estimate for the project is $485,000. The re-design requires that we acquire more property from some owners, which is in process. The Right-of-Way process is ongoing.
Page Updated: 11/11/20
TASK | DURATION (DAYS) | COMPLETION DATE |
Complete final design | Tuesday, December 15, 2020 | |
Accept final bids | 14 | Tuesday, December 29, 2020 |
Award contract | 3 | Friday, January 1, 2021 |
Notice to proceed | 21 | Friday, January 22, 2021 |
Construction complete | 119 | Friday, May 21, 2021 |
Town of Davidson
Doug Wright, Project Manager
Consultant
Dewberry